We have endured timing setbacks over the last few months mainly due to the very wet Spring and thus the knock on effect on work programmes.

GJP made a fantastic job of the second phase of the construction including piles,pontoons and services and now we have completed pathways and drainage works the "site" is looking great and continues to receive many compliments.

Currently we are waiting for opposite bank protection to be installed at our entrance structure before our Network access agreeement is finalised with CRT.

Our new power supply is waiting to have a CT meter installed and then we shall be "illuminated under the hours of darkness"

Our new facilities block containing showers,toilet and laundry is complete with the aid of funding from "Worcestershire County Council "Leader" - Rural Development Programme for England.

Landscaping is almost complete with surface wearing course to be placed on the car park and access track.

We anticipate opening late July, early August subject to CRT and the NAA being finalised.